Planning Shifts of Collections:
3rd Shift
- closed Lib March 19-27, 94
- moved Reference desk and coll
- moved juv curric
- moved ILL
- moved Reserve
- moved Curent Periodicals
- moved Lib admin
- moved Personnel
- moved Lib copy svc
- moved Circ desk
- moved AcS staff area
Here's a list of things that had to happen sequentially; a timeline
of sorts. Typos or spellos don't matter; you just want to give a copy
of what every moving part is responsible for to each party.
List of Sequentials for Christmas Shift
When Possible:
Library:
- Move Newspaper Microfilming Project
1st week in March:
SDDeacon:
- Reubensteins install floor covering over switchmats in Circ lobby
Library:
- Smith Bros install panel systems for ILL, Lib Office, Admin Svc,
and Lib Copy Svc, Circ/Res, etc.
3M:
- install 6 switch mats in circ lobby (2031). ARB says they're
supposed to be here very soon; he put thru a request thaty they come
down.
Wednesday, March 16:
Library
- Staff in various offices move personal work areas into new space
Smith Bros:
- finish installing Steelcase systems in Reserve, lib Office, ILL,
LCS, AdmSvc, and Circ offices.
Thursday, March 17
Library:
SDDeacon:
- empty and clean ACMR. Install temp data wiring. Must be done by
this day.
Don:
- clear a path to the bookchute: will begin using it Monday,
03/21
Friday, March 18:
SDDeacon:
- In early afternoon, temp wall in north end of reserve room gets a
door knocked into it. Plastic covers doorway for remainder of
afternoon.
Library:
- Library closes at 6pm. Signs placed on doors about closure,
directing patrons to east front door on Monday for paging. Caution
tape put on doors so staff and others don't try to use them.
Saturday, March 19:
Library:
- Systems moves and sets up Reserve terminals
- Systems moves Ref CDRoms, pc's, terminal out of oldRef into
newRef.
- Task Desk set up at Reserve Desk location
- Volunteer sign-in desk set up in marble lobby.
- CircRes staff process reserves
SDDeacon:
- take down Ref/Docs wall
- Rubensteins finish carpets in newRef and Docs space
- move the erected but not placed Spacesaver shelving into place and
affix transverse tie struts across top
Moving Company: (at night)
- take all CDRom/pc furniture from oldRef to newRef (clearing
the floor for shelving
- move three Stacks desks to ACMR and two stacks desk to storage
- move eight individual study desks and chairs to newReserve
from OldReserve
Sunday, March 20:
Library:
- Systems gets all circ terminals except checkin terminal
operational in new area
- Systems moves LWilley's pc
- Systems begins setting up Ref CDRoms, etc. in new Ref
- more of the Saturday stuff for CircRes
Monday, March 21:
SDDeacon:
- 6am: old Ref Desk demo'd and dumped.
- no earlier than 8am, and no later than about noon, get the outside
temp book chute glued shut somehow.
- demo the east temp wall of Reference
- lay carpet in area where temp wall used to be (between newRef
and oldReserve).
Spacesaver:
- erect new sorting area shelving
- erect current periodicals 20 sections and 2,640 backstops and
2,640 shelves
- erect 4 sf bills/fines sections in Circ area 105C
Library:
- as soon as outside bookcute glued shut, Systems moves terminal 132
(checkin terminal) to new space and sets up
- have elevator people change floor numbers in the elevator
- Front East entrance opened. Signs directing to Task Desk
- Systems begins Ref CD's, pc's, etc.
- Nearly half of the Reference collection must be shifted
- IMC staff working on own shift
- Staff move stuff from personal offices, where possible
- Books coming off reserve are placed on study tables in oldReserve
by AcS staff
- AcS staff move PB's and PF's into new Reserve tunnel
- Systems moves Lib Personnel and Lib Admin pc's, etc., and Howard
Lindstrom's pc, so furniture can be moved at night.
Moving company: at night
- 1st: LWilley's office
- 1st: All CircRes staff furniture which doesn't go to storage
- 2nd: SStigall's office
- 2nd: Current Periodicals work area from Mary's cage to Newspaper
work area
- 3rd: Lib Office & Lib Personnel begin
- 34d: HLindstrom's office 36A
D Arnold:
- take the detection gate down from oldReserve; stash in the
circular stairway on 2nd floor
- remove the turnstile from oldReserve and move to storage
Tuesday, March 22:
Library:
- Ref collection other half almost finished today
- Circ staff empty all shelves on temp walls in oldCirc
- 1 Reserve collection shift
- 2 IMC staff moving IMC collection
- begin moving current periodicals
- staff move stuff from personal offices, when possible]
- Index table books get put on floor or other study tables
- Task Desk staff put labels for CurPer shelving
Galifco:
- install new industr
- finishes periodicals shelving
Moving Compan (at night):
- move Reference furniture
- move Lib Personnel and Lib Admin Office furniture
Wednesday, March 23:
Library:
- end Reference shift
- staff move stuff from work areas, where possible
- 5 shifts of Juvie/Currics
- 1 shift of LCS collection
- 4 shifts of CurrPer
- Task Desk staff put labels for CurPer shelves
- 2 IMC staff moving IMC collection
SDDeacon:
- if not done, dome east tem wall from newRef/oldRes
- Move building supply stuff into old Res
- lay carpet in area where temp wall used to be
Spacesaver:
- finish Juvie/Curric shelving
- misc. other shelving
Moving Company (at night):
- index tables from oldRef to newRef
- Lib Copy Svc
- ILL
- Halff the public study tables from oldRes to newReserve
- Circ/Reserve storage items to storage staging area
- IMC
Thursday, March 24:
Library:
- Juvie/Currics move
- CurPer move
- staff move personal offices
- Task Desk staff make CurPer labels
- 2 IMC staff moving IMC collection
- Index table books moved from floor to index tables in newRef
DArnold:
- install dectection exit gate from oldReserve in cherry entrance
on 2nd floor south
SDDeacon:
- temp walls on 2nd Floor South start coming down. Don't take
down ILL walls; leave this room for storage until FinalKnight.
Remember there's an annunciator panel on one of the temp walls. Temp
walls also means ramps, near temp entrance, both inside and outside
- LHMorris demos power on 2nd floor south; see JHelmer
Smeed:
- demo data lines on 2nd floor south; see JHelmer
Moving Company (at night):
- move Admin Svc
- Move half the publi study tables from Reserve to newRes
- IMC
- Graphic Arts
- Staff Lounge
- Newspaper Project
Friday, March 25:
Library:
- finish curPer shift
- Admin Svc shift
SDDeacon:
- in early morning, Reubensteins cut carpet for switch mat placement
on 2nd Floor south
- in the afternoon, redo the carpet over the switch mats
- temp doorway into OldRes from east hallway boarded up
- temp wall separating oldReserve from microforms put up, keeping
the oldRes office and Adaptive Tech Lab room accessible.
- Eugene Mirro and Glass infil temp doors with windows
3M:
- install switch mats on 2nd Floor south
- during the morning, install 2 exits in circ lobby (2031), two
remote alarms, 1 single corridor exit system and remote alarm for
circ/Spc elevator
- install entrance system on 2nd floor south. These 3M installs
can go into Sat and Sun, if needed
- tweek exit gate on 2nd south, and entrance also on 2nd south
Saturday, March 26:
- final fluffing of work stations, offices, collections, public
areas
- PhyPlant custodians clean carpet everywhere they find it, both in
renovatedKnight and CurPer Reading Room
Sunday, March 27:
- more of the Sat fluffing
- more of the PhyPlant carpet cleaning
Postbreak:
Postbreak stuff can happen during the intersession, as soon
as the areas are empty and/or ready:
SDDeacon:
- Dorman take down temp walls from Personnel and Lib Admin Offices
on 4th floor.
- Dorman move emptied shelving from old CurPer and Juvies, etc. to
4th florr and install them, or to 3rd floor, for later reinstall
Library:
- move microcomputer support
Back to Shift Planning main page
Page created by sstevens@darkwing.uoregon.edu
Last substantive update: 970506