2026 ONYX LN2 Gaseous Delivery Monitoring

System Strategy: Vaporization Phase Auditing & Compliance

Phase 1: Winter/Spring Audit (Completed)

Duration: December 31, 2025 – April 3, 2026

MetricGround Truth (Totalizer)Logger Integration
Start (12/31/25)0 SCF0 SCF
Mid-Point (01/12/26)105,935 SCF105,274 SCF
End (04/03/26)923,190 SCF931,292 SCF
Variance-0.87% (Logger High)

Audit Notes: The 0.87% variance is well within the ±1% factory specification. A slight "over-counting" drift was observed as ambient temperatures rose from 28°F in January to 62°F in March. Data resolution was found to be 4.5 minutes due to an interval setting error in Phase 1.

Jan 12 Calibration Point
Jan 12 Snapshot
Final Phase 1 Totalizer
Final Totalizer: 923,190

Phase 1 Assets: Raw CSV Data Binary .DAT File Initial Strategy PDF

Phase 2: Spring/Summer Audit (Active)

Status: Initialized April 3, 2026 @ 3:00 PM

Phase 2 Software Settings
Verified 120s Interval
Logger Hardware Check
New Battery & LED Heartbeat

Phase 2 Assets: Configuration XML Scaling Documentation

📅 Next Retrieval Deadline: June 30, 2026
Add June 30 Reminder to Calendar